LOTO Permit Status
 
Permit Number
Date Created
Date Needed
RI
Company Name
Project Name
Building
Scope of Work
Comments
 
Submitted  (7 LOTO Permit Applications) 
LP-3013 01-19-2018 02:36 PM 01-30-2018 Wright, Bill W.E. Lyons 37 Cooling Tower Generator replacement 37 LOTO new genset until evap.
 Negative starter ground lead is removed from the starting battery. We will LOTO this with a cord cap loto device and lock.
This will prevent generator from starting and supplying power.
 
LP-3012 01-19-2018 02:21 PM 01-29-2018 Wright, Bill W.E. Lyons 37 Cooling tower replacement 37 move lighting photocell to avoid new chilled water piping on the north wall [JAN-19-18 Bill Wright]  we expect only the one control circuit in the LB fitting before the photocell
LP-3011 01-19-2018 12:56 PM 01-25-2018 Wright, Bill W.E. Lyons 37 Cooling Tower Generator replacement 34 this new RETURN  valve is to LOTO'd after a hot tap operation.
The valve will remand LOTO'd until the 6 " chilled water supply and return lines are completed and accepted to the new heat exchanger at bldg 37
This LOTO is a
 
LP-3010 01-19-2018 11:14 AM 01-25-2018 Wright, Bill W.E. Lyons 37 Cooling Tower Generator replacement 34 this new SUPPLY valve is to LOTO'd after a hot tap operation.
The valve will remand LOTO'd until the 6 " chilled water supply and return lines are completed and accepted to the new heat exchanger at bldg 37
 
LP-3008 01-18-2018 07:15 AM 01-18-2018 Stanley, Gregory Steris Corp PM on B-100 Autoclave Steam Generator 100 Perform preventative maintenance.  
LP-3007 01-17-2018 01:56 PM 01-23-2018 Wright, Bill W.E. Lyons B37 ALS Cooling Tower Replacement 37 close riser valve to CT-103 to install orifice  plates on hot water riser at top of tower [JAN-18-18 Bill Wright]  this loto is the same as LP-2962, completed earlier in the project
LP-3006 01-17-2018 01:45 PM 01-23-2018 Wright, Bill W.E. Lyons B37 ALS Cooling Tower Replacement 37 close riser valve to CT 102 to install new orifice plates on hot water riser at top of tower [JAN-18-18 Bill Wright]  This loto is the same as LP-2963, completed earlier in the project
On hold by RI  (7 LOTO Permit Applications) 
LP-2940 09-08-2017 05:01 PM 09-14-2017   Total Environmental & Power Systems, Inc: (TEPS) B. 68/82 Fuel Tanks Replacement 68 Subcontractor to demo existing electrical conduit and add new circuit breakers for the new Fuel Tank and the Fuel Station.  
LP-2877 07-07-2017 12:51 PM 07-14-2017 farrell, randy PDE EPO phase 2 59 Loto exposed circuits while working on EPO junction box [JUL-07-17 Doug Burkhardt] The panelboard names for the isolation points do not match the panel schedules or the single line diagram.
Arc Flash data is missing.

[JUL-31-17 randy farrell]         Panel No.:    U592A
Bldg. No.:    59
Location :    1st Level North Electrical Room
                FSD COMP LVL   
A    20    20   
       
This is from LBL data base. Do you have different numbers?
   

[JUL-31-17 randy farrell] Panel No.:    E594A
Bldg. No.:    59
Location :    1st Level South Electrical Room

        Used for: / Room #        Trip&    Ckt
                Frame    #
        SHUNT TRIP POWER           
1        TO EPO        20    1
This is also copied from Maximo. what am I doing wrong ?
LP-2744 11-22-2016 07:05 AM 11-23-2016   PDE B100 EL1D-25/27 Reconfiguration 100 Replace existing single pole 20 amp breakers with new two pole breaker and pull new wire properly sized for circuit rating.  
LP-2658 09-09-2016 10:59 AM 09-13-2016 Tully, John   B77 Skid Controls B77 Skid Replace transformers in control panel with new in their own enclosures within the control panel  
LP-2307 09-01-2015 01:57 PM 09-01-2015 magstadt, michael Nationwide Power   50A Routine inspection, testing, preventive maintenance of the 60KVA Eaton 93E Uninterruptible Power Supply (UPS), including Extended Battery Cabinet (EBC) and battery replacement.  
LP-1971 05-20-2015 01:11 PM 05-20-2015 Johnson, Katherine Infrequent Subcontractor     Make this to the point.  Additional info can be written below.

This should describe the area that work will be performed based off the isolations locked out.

If the work is such that it will take place in separate phases (i.e. shut off valves to add new valves and then LOTO out the new valves) and the LOTO Safe Zone will shift, then a new Permit must be prepared for each planned shift.
 
LP-1956 05-13-2015 03:08 PM   Perkins, Kat          
Reviewed by EHS  (7 LOTO Permit Applications) 
LP-2982 11-09-2017 03:55 PM 12-12-2017 Wright, Bill Crouse Construction 50 B Gas Switch Replacement 50 B Currently, the gas switch is "bypassed " .
1. This LOTO is to re-configure 12 KV T body splices  and splice in new cables to the new Gas switch in Manhole 59 .
2. Test final cable/ term / switch configuration.
 
[JAN-17-18 James Murphy] Changed Arc Flash to reflect the LOTO of 52-A606
LP-2948 09-11-2017 02:23 PM 09-14-2017 Huebschle, Mark CAL NEVA 77A HVAC upgrade 77A Work from scissor lift between crane rails [SEP-11-17 James Murphy] Need equipment name in description.

[SEP-12-17 James Murphy] Isolation descriptor does not match Areas Affected or Equipment Name

[SEP-14-17 Mark Huebschle] Panel schedule changed
LP-2947 09-11-2017 02:15 PM   Huebschle, Mark CAL NEVA 77A HVAC upgrade 77A Work off of a scissor lift between the crane rails [SEP-11-17 James Murphy] Need equipment name in description

[SEP-12-17 James Murphy] Isolation descriptor does not match Areas Affected or Equipment Name

[SEP-13-17 Katherine Johnson] CB 40 controls CR-001-77A according to the panel schedule. 

[SEP-14-17 Mark Huebschle] Panel schedule changed
LP-2922 08-21-2017 09:52 AM 08-21-2017 Kovacic, Michael Infrequent Subcontractor Electron Microscope. 67 Rebuilding the FEG TANK. [AUG-21-17 Katherine Johnson] Approval of Permit should have been performed by acting AHJ.
LP-2889 08-02-2017 08:59 AM 08-11-2017 Kemper, Timothy Rudolph & Sletten (R&S) IGB 91 Drain the line from HY12
Cut domestic water main in the street
Install tee and valve for IGB utility service
[AUG-04-17 Doug Burkhardt] Approved per MCD

[SEP-20-17 Katherine Johnson] Un-approve to allow for corrections.

[SEP-20-17 Doug Burkhardt] Approved per MCD.
LP-2850 06-13-2017 02:28 PM 06-14-2017 Johnson, Katherine Infrequent Subcontractor 70A Autoclave 70A Inspect wiring and change out a set of wires on a water level control board as well as install Water level probes.  

This will be done by the vendor under the direct field supervision of an LBNL QEW1 (or greater).  The QEW will establish an electrically safe work condition before any wiring work is performed.
 
LP-2804 04-14-2017 01:31 PM 04-18-2017 Stanley, Gregory Infrequent Subcontractor Mass Spec UPS Battery Replacement 100 Replace UPS batteries.   
Approved  (1150 LOTO Permit Applications) 
LP-3009 01-18-2018 11:46 AM 01-22-2018 Wright, Bill W.E. Lyons 37 Cooling Tower Generator replacement 37 lock out load bank breaker only. Do not disable generator.
This will be used to loto old wire, ZVV, work in old j-box to modify conduit. Then, LP-3005 will be used after the conduit is finished. LP-3005 does disable genset.
Once LP-3005 work is completed, this loto RI lock will be re-installed until all work is finsihed down stream and EVAP of the new load bank is completed.
[JAN-19-18 James Murphy] This isolation was reviewed by Facilities under LP-3005 and was split at my request.
LP-3005 01-12-2018 12:24 PM 01-16-2018 Wright, Bill W.E. Lyons CT-102 and CT103 replacement 37 old load bank wiring was partly removed to a j box. PDE need to remove the old wire from the genset and extend the conduit into a new 'load bank selector switch."
Later we will need to loto this again to pull in the new wire and complete terminations
 
LP-3004 01-10-2018 03:02 PM 01-17-2018 liljefelt, mark Infrequent Subcontractor B054 Dishwasher Repair B054 Make repairs to the dishwasher [JAN-12-18 Doug Burkhardt] I updated the isolation points as it was incorrect. The correct notation for circuit 16 is 446A5A-16, not 446A5A16A.

[JAN-12-18 Doug Burkhardt] There is a disconnect in front of the equipment. SLD and Panel schedules are now updated.
LP-3003 12-20-2017 08:41 AM 12-22-2017 farrell, randy XL Construction Heat exchanger and pumps 59 LOTO ISOLATION valves to install new piping [DEC-20-17 Doug Burkhardt] Approved per MCD.
LP-3002 12-20-2017 08:34 AM 12-22-2017 farrell, randy XL Construction Heat exchanger and pumps 59 LOTO ISOLATION valves to install new piping [DEC-20-17 Doug Burkhardt] Approved per MCD.
LP-3001 12-20-2017 08:24 AM 12-22-2017 farrell, randy XL Construction Heat exchanger and pumps 59 Close ISOLATION valves to install new piping [DEC-20-17 Doug Burkhardt] Approved per MCD.
LP-3000 12-20-2017 08:14 AM 12-22-2017 farrell, randy XL Construction Heat exchanger and pumps 59 LOTO 2 ISOLATION valves and upgrade piping @ HX2 [DEC-20-17 Doug Burkhardt] Approved per MCD.
LP-2999 12-20-2017 08:07 AM 12-22-2017 farrell, randy XL Construction Heat exchanger and pumps 59 Close ISO valves to install new piping on new CWGP-3 [DEC-20-17 Doug Burkhardt] Approved per MCD.
LP-2998 12-18-2017 12:10 PM 12-19-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) Troubleshoot SW-A1 Line 1 PT's and cell 036 After energizing Line 1 in SW-A1 there is a buzzing or rattling sound coming from the cell that the PT's and PT transformer are located.  We are going to do a hot transfer at SW-A1 outting the hill on line 2 and then we will de-energize the bank 1 transformer to de-energize the line going from the line 1 potheads to breaker 52-A101 which is the line that energizes these PT's so they can inspect the cell.  the test results on this equipment came back good therefor we think it may be some loose sheetmetal withing the cell.  [DEC-19-17 James Murphy] The Switch Tag will need to be corrected and reviewed by Electrical Saftey prior to switching.
LP-2994 12-06-2017 10:22 AM 12-08-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) SW-A1 Line 2- 3 Year PM 036 3 Year Preventative Maintenance on SW-A1 Line 2 and SW-A2 Line 2 which include:
12kV Breakers and Cells
SW-A1 Bus 2 PT's and CPT's
SW-A2 Bus 2 PT's and CPT's
SW-A1Line 2 Bus and Relays
SW-A1Line 2 Bus and Relays
12kV Line conductors from Line  2 Pothead to 52-A102
[DEC-08-17 James Murphy] Correct LOTO Permit number on Line #14
Correct Line number on Line #16
Add Line between #18 & #19 to re-Test HV Probe
Add location of Ground G3 to One Line
Engineer to review Arc Flash values and Working Distance for electrical isolations #6 & #7

Correct and resubmit with signature of a Current QEW 3 Review.

[DEC-08-17 James Murphy] Unapproved so requester can make corrections
LP-2993 12-06-2017 05:56 AM 12-07-2017 farrell, randy XL Construction Heat exchanger and pumps 59 LOTO valves 1-053 and 1-0400 on bypass to remove bypass section. Install blanks for secondary protection. [DEC-06-17 Doug Burkhardt] Approved per MCD.
LP-2992 12-04-2017 01:19 PM 12-11-2017 Samatua, Tipasa CAL NEVA 90 Heat pump replacements 90 Adjust sheave [DEC-05-17 Katherine Johnson] What panel and circuit breaker is the disconnect fed from.

[DEC-06-17 Tipasa Samatua] Please see attached electrical drawings. This is a new project that is ongoing and as builts are not updated yet. 

[DEC-06-17 Katherine Johnson] Since this is a 480V system, a "Standby Person" will need to be briefed on where to shut off upstream if things go bad during ZVV.  This person will need to know where to go.  That info should be on the permit so that can be covered in the briefing.  I've sent a note to electrical engineering so they can advise.
LP-2991 12-04-2017 01:15 PM 12-11-2017 Samatua, Tipasa CAL NEVA 90 Heat pump replacements 90 Adjust sheave [DEC-05-17 Katherine Johnson] What panel and circuit breaker is the disconnect fed from.

[DEC-06-17 Tipasa Samatua] Please see attached electrical drawings. This is a new project that is ongoing and as builts are not updated yet. 

[DEC-06-17 Katherine Johnson] Since this is a 480V system, a "Standby Person" will need to be briefed on where to shut off upstream if things go bad during ZVV.  This person will need to know where to go.  That info should be on the permit so that can be covered in the briefing.  I've sent a note to electrical engineering so they can advise.
LP-2990 11-30-2017 10:48 AM 12-08-2017 Marietta, Peter Infrequent Subcontractor Repair of hard-wired BSC 977 Repair to the Biosafety Cabinet will be performed by the TSS Tech.  A Lab QEW will perform the zero energy verification and provide Direct Field Supervision (outlined in section 6.11 of the LBNL Electrical Safety Manual) to the Tech if work on wiring will be performed.   
LP-2989 11-29-2017 01:39 PM 12-04-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) SW-A1 Line 1- 3 Year PM 036A 3 Year Preventative Maintenance on SW-A1 Line 1 which include:
12kV Breakers and Cells
Bus 1 PT's and CPT's
Line 1 Bus and Relays
12kV Line conductors from Line 1 Pothead to 52-A101
[DEC-01-17 Doug Burkhardt] The LP and the arc flash do not match. Please verify that the label in the field and the data in the model exist. Separate email sent to Ryan.
LP-2988 11-22-2017 09:51 AM 11-15-2017 Samatua, Tipasa CAL NEVA B. 67-5210A Bio Safety Cabinet 67 Subcontractor to connect new  N2 line for the new Bio Safety Cabinet [NOV-28-17 Doug Burkhardt] Per MCD, corrections required.

[DEC-11-17 Doug Burkhardt] Approved per MCD.
LP-2987 11-17-2017 01:24 PM 11-28-2017 Kemper, Timothy Rudolph & Sletten (R&S) IGB 91 Pull temporary power cables in trench and land at 511A. [NOV-28-17 James Murphy] Arc Flash needs to be reviewed by Facilities Engineering, Arc Flash Data Base is inconsistent.

[NOV-28-17 Doug Burkhardt] AF by JH

[NOV-28-17 Keith Laforga] Use of a remote switch at 511A and 512A at 5' working distance will effectively lower the incident energy down to 14 cal/cm2
LP-2986 11-17-2017 10:28 AM   Samatua, Tipasa CAL NEVA B. 67-5210A Bio Safety Cabinet 67 Subcontractor to install a new Emergency Bugeye in room 5210A  
LP-2985 11-17-2017 08:16 AM 11-30-2017 Samatua, Tipasa CAL NEVA B. 67-5210A Bio Safety Cabinet 67 Subcontractor to connect new Transformer for new airflow monitor for a new Bio Safety Cabinet and convert one outlet to duplex  
LP-2984 11-13-2017 11:01 AM 11-13-2017 Johnson, Katherine Siemens - Building Technoligies MRI Chiller Maintenance 55A Emergency repair of the Chiller by a non-QEW Siemens employee supervised by a lab QEW.  
LP-2983 11-10-2017 07:31 AM 11-15-2017 Wright, Bill Crouse Construction 72C-169 Microscope installation 072C 120V spot light fixture, is being re-located into a different 2x4 ft  drop in ceiling tile.  
LP-2981 11-02-2017 04:51 AM 11-02-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Tie in new receptacles on roof to existing roof top junction boxes where previous circuits occurred prior to old cooling tower demolition.  
LP-2980 10-31-2017 08:28 AM 10-31-2017 Kemper, Timothy Rudolph & Sletten (R&S) IGB B91 Tie in 10" waterline to new valve installed by M&H 
Located on Smoot Rd
[OCT-31-17 Doug Burkhardt] Approved per MCD.
LP-2979 10-24-2017 11:46 AM 11-01-2017 drkranz@lbl.gov Johnson Controls/York 34 ARU 004 refrigerant leak repair 034 Repair refrigerant leaks on the chiller(vendor).
Annual PM inspection and cleaning(HVAC shop).
[NOV-01-17 James Murphy] added chilled water valves
LP-2978 10-24-2017 10:23 AM 11-07-2017 rcvelasco@lbl.gov Johnson Controls/York 34 ARU 003 refrigerant leak repair 34 Repair refrigerant leaks on the chiller(vendor)
Annual PM inspection and cleaning(HVAC shop)
[NOV-01-17 James Murphy] Unapproved to add correct isolation
LP-2977 10-23-2017 12:41 PM 10-24-2017 Bolles, Benjamin W.E. Lyons B37 Generator Replacement 37 If rotation is incorrect turn off and LOTO  temporary generator and correct rotation.  
LP-2976 10-20-2017 01:23 PM 10-24-2017 Wright, Bill Crouse Construction 72C-169 Microscope installation 072C line 1 .need to remove and re-locate a 120 V can light from one ceiling tile to a new locations 2 feet away. The flex conduit and wire, may be too short and may need to be replaced.

line 2. On 277 v fixture, extend flex longer to avoid new opening in ceiling tile. Fixture to stay in current place.
[OCT-31-17 Bill Wright]  added additional 277 V light fixture LOTO point . The flex conduit will need to be lengthened 

[OCT-31-17 James Murphy] Returned for Facilities review due to additional isolation.

[OCT-31-17 James Murphy] Bill, please provide additional scope for new isolation. Arc Flash and panel schedule reviewed and correct.

[OCT-31-17 Bill Wright]  added scope to line 2 fixture
LP-2975 10-19-2017 10:44 AM 10-20-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Connect new exterior cooling tower lights to existing exterior lighting junction boxes.  
LP-2974 10-19-2017 09:05 AM 10-27-2017 Samatua, Tipasa Total Environmental & Power Systems, Inc: (TEPS) B. 68/82 Fuel Tank Rpl 68 Subcontractor to connect power to the new Fueling Station at building 68.  
LP-2973 10-17-2017 12:27 PM 10-23-2017 Jew, Ernie Nite & Day Power PM on MGE UPS at OSF 943 Perform Preventive Maintenance on MGE 800kVA UPS at OSF  
LP-2972 10-16-2017 10:54 AM 10-16-2017 Johnson, Katherine Infrequent Subcontractor Maintenance on Washer 977 Replace a heating element  
LP-2971 10-12-2017 10:40 AM 10-19-2017 Kemper, Timothy Rudolph & Sletten (R&S) IGB 91 Install temp power for the IGB/MUP site [OCT-12-17 Timothy Kemper] A. 0715 on19-OCT-2017 Loto breaker, re-energize at approx 1500 
B.0715 on 20-OCT-2017 Loto breaker, re-energize at approx 1500 

[OCT-12-17 Doug Burkhardt] Arc Flash data is missing.

[OCT-17-17 James Murphy] Major changes made to isolation, resubmit for Facilities review

[OCT-18-17 Katherine Johnson] See comments above
LP-2970 10-12-2017 10:33 AM 10-19-2017 Kemper, Timothy Rudolph & Sletten (R&S) IGB 91 Installing temp power for IGB/MUP [OCT-12-17 Timothy Kemper]  This shut down LOTO main at Bank 511 on 19-Oct-2017,
Then  remove LOTO on 25-Oct-2017 during EVAP

[OCT-12-17 Doug Burkhardt] Arc Flash data is missing.

[OCT-17-17 James Murphy] Major changes made to isolation, resubmit for Facilities review
LP-2969 10-12-2017 08:37 AM 10-12-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Re-route control cables for liquid level control out of VFD and into control cabinet through new raceway. [OCT-12-17 Katherine Johnson] Duplicate of 2952 with an updated scope of work.
LP-2968 10-11-2017 06:19 AM 10-13-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Re-route control cables for liquid level control out of VFD and into control cabinet through new raceway.  
LP-2967 10-06-2017 11:11 AM 10-09-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Relocate conductors from junction box in 1st floor generator room to new electrical panel E231A4A in generator room fed from E231A-4 in 2nd floor electrical room. [OCT-09-17 Katherine Johnson] Doug and Murphy were both out of the office.
LP-2966 10-04-2017 01:58 PM 10-10-2017 Wright, Bill Stations bld 7 to bld 46 moves 046 we need to LOTO (4) 120 v - 20amp circuits in two panels. These feed four cubicals. The contractor will be changing outlets and jumpers in the furniture, to address circuit layout.  
LP-2965 10-02-2017 10:40 AM 10-09-2017 Brunkow, Douglas Goebel Paving/Grading Old Town Phase 3 Street outside buildng 7 Loto the 8 inch High Pressure City Water (HPCW) line in Segre road to excavate soil in the vicinity of the line. [OCT-03-17 Doug Burkhardt] Approved per MCD
LP-2964 09-29-2017 07:48 AM 10-02-2017 Kemper, Timothy Rudolph & Sletten (R&S) IGB B59 LOTO 10" HPCW valve that services IGB for work on line down stream.

[SEP-29-17 Doug Burkhardt] Approved per MCD.
LP-2963 09-27-2017 11:42 AM 09-28-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Close riser valve to CT 102 to install reducing washer on hot water riser at top of tower. [SEP-28-17 Doug Burkhardt] Approved per MCD.
LP-2962 09-27-2017 11:38 AM 09-28-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Close riser valve to CT 103 to install reducing washer on hot water riser at top of tower. [SEP-28-17 Doug Burkhardt] Approved per MCD
LP-2961 09-26-2017 03:39 PM 09-26-2017 Brunkow, Douglas Goebel Paving/Grading Utility corridor outside building 14 Repair a damaged 1-1/4 inch gas line feed to the Fire House from the main line. [SEP-26-17 Mark Scott] Facilities Manager Review performed by Dean Sedlachek as designated by Mike Dong.
LP-2959 09-21-2017 01:16 PM 09-21-2017 Johnson, Katherine Infrequent Subcontractor Maintenance on Washer 977 PM of the washer.  This will include positioning the insulated power leads so a probe can be easily slid over each phase to measure amperage. The positioning of the wires is done with the power off. The probe is approximately 10" long so no body parts come within 3".  
LP-2958 09-21-2017 12:45 PM 09-21-2017 Kemper, Timothy Rudolph & Sletten (R&S) IGB 91 Tie-in new 10" water to IGB. [SEP-21-17 Doug Burkhardt] Approved per MCD
LP-2957 09-21-2017 12:32 PM 09-21-2017 Kemper, Timothy Rudolph & Sletten (R&S) IGB B50 Vent air from new HPCW tie- in  to IGB /B91 [SEP-21-17 Doug Burkhardt] Approved per MCD
LP-2956 09-19-2017 05:13 AM 09-19-2017 Bolles, Benjamin W.E. Lyons B37 Generator Replacement 37 Open main breakers on EG 73 37 generator and temporary rental generator so that the contractor can remove the cover off of panel EG73A and take a picture of the main breaker.  
LP-2955 09-18-2017 09:10 AM 09-22-2017 Samatua, Tipasa Crouse Construction B. 83 Renovation 83 Subcontractor to install a new Battery Back up Emergency Light (Bug eye) at the exterior door of building 83 (Loading Doc)  
LP-2954 09-15-2017 11:46 AM 09-15-2017 Bolles, Benjamin W.E. Lyons B37 Generator Replacement 37 Disable EG 73 37 and connect temp generator for fuel tank removal.  
LP-2953 09-14-2017 08:07 AM 09-15-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Demolition of exterior light on roof top of B37.  
LP-2952 09-13-2017 07:36 AM 09-15-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Currently Main Breaker is open on this panel.  Main breaker will be closed to energize three pumps GP 144, GP 145 and GP 146.  Prior to energizing pumps, CT 103 will be locked open for future work on CT 103 VFD.  
LP-2951 09-12-2017 12:56 PM 09-13-2017 rcvelasco@lbl.gov Infrequent Subcontractor TSW-1-55 Transfer Switch Repair 55 Helmuth is going to do repairs to this transfer switch during our 9-16-17 outage.  
LP-2950 09-12-2017 09:34 AM 09-14-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Connect new cooling tower CT 102 tower water piping to new cooling tower CT 103 tower water piping.  Connect supply and return piping to new heat exchanger on roof. [SEP-14-17 Doug Burkhardt] Approved per MCD.
LP-2949 09-11-2017 02:27 PM 09-14-2017 Huebschle, Mark CAL NEVA 77A HVAC upgrade 77A Work from scissor lift between crane rails [SEP-11-17 James Murphy] Need equipment name in description.
LP-2946 09-11-2017 01:28 PM 09-15-2017 farrell, randy XL Construction Heat exchanger and pumps 59 LOTO brkr in prep for EVAP  
LP-2945 09-11-2017 01:23 PM 09-15-2017 farrell, randy XL Construction Heat exchanger and pumps 59 LOTO brkr in prep for EVAP  
LP-2944 09-11-2017 01:20 PM 09-15-2017 farrell, randy XL Construction Heat exchanger and pumps 59 LOTO new brkr in prep for EVAP  
LP-2943 09-11-2017 10:23 AM 09-15-2017 farrell, randy XL Construction Heat exchanger and pumps 59 Loto valves CWR 1-066 and CWS 1-067 to remove blank flanges, weld in temp valves reinstall blank flanges with new drain valves [SEP-11-17 Doug Burkhardt] Approved per MCD
LP-2942 09-10-2017 10:51 AM 09-20-2017 Samatua, Tipasa Total Environmental & Power Systems, Inc: (TEPS) B. 82 Fuel Tank Replacement 82 Subcontractor to install/provide new power to the new Fuel Tank and the Remote Fill Station at building 82. [SEP-11-17 James Murphy] This isolation will affect 116A1A40B also B81. On HOLD for Facilities review.

[SEP-19-17 Tipasa Samatua] The building 81 WAA and the Emergency Storage Container Group will be notified with the duration of the shutdown. Approximately 2 hours down time before we schedule the work.
LP-2941 09-08-2017 05:12 PM 09-14-2017 Samatua, Tipasa Total Environmental & Power Systems, Inc: (TEPS) B. 68/82 Fuel Tank Replacement 68 Subcontractor to remove electrical conduits and J-boxes and install a new circuit breaker for an new Remote Fill Station at building 68. [SEP-11-17 Doug Burkhardt] Isolation does not match panel schedules and SLD.

[SEP-13-17 Tipasa Samatua] What are you doing to correct this? Please advise. 

[SEP-18-17 Tipasa Samatua] It is my preference as a Construction Manager to perform the LOTO at panel 217A2A1A C/B 9 from building 75-120. and not the disconnect switch for the XFMR (Bank 408 disconnect).
LP-2939 09-08-2017 09:28 AM 09-11-2017 Huebschle, Mark CAL NEVA B90 Heat Pump replacements 90 Install new FPU panel, FPU-006C-90  
LP-2938 09-07-2017 04:35 PM 09-11-2017 Huebschle, Mark Infrequent Subcontractor B50 steam leak repair 50 Secure steam heat boilers for work on steam condensate return piping  
LP-2937 09-07-2017 03:21 PM 09-13-2017 Stanley, Gregory PDE Northen Fit-Up 144 100 Install new circuit breaker in panel L1F, install conduit and run new circuit with a 50 amp receptacle in Room 144.  
LP-2936 09-06-2017 01:46 PM 09-13-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) SW-A6 Line 1 Maintenance 064C Emerson to perform Electrical 3 Year PM on:
A.  SW-A6 Bus 1 (12KV Breakers, CPT's, PT's, Metering Equipment)
B.   ADF-1-55, Bank 513
C.  GS-3-71, ADF-1-71, ADF-2-90, ADF-3-90, GS-2-71, Bank 
     90, Bank 514
D.  ADF_2-51, ADF-1-51, Bank 512
E. Bank 511
 
LP-2935 09-06-2017 12:33 PM 09-08-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) SW-A6 Line 1 Maintenance 064C Only Work performed under this LOTO will be ZVV at ground carts as well as hanging of the ground clusters on the ground carts that are listed on the permit.  
LP-2934 09-06-2017 09:47 AM 09-14-2017 Wright, Bill PDE Gas switch replacement 50B parking structure We need to relocate a 120 V GFCI on the wall of Gas Switch GS-1-50B. We need to re-route the 1/2 conduit, box, outlet etc . This wall will be removed . A new fence structure will be installed to protect the new replacement gas switch.  
LP-2933 09-05-2017 08:17 AM 09-05-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) SW-A6 Bank 511 Maintenance 064C Perform 3 Year Maintenance on Bank 511 Transformer and the Secondary Main Switch gear and Breakers  
LP-2932 08-31-2017 12:39 PM 09-05-2017 Brunkow, Douglas PDE Flexlab PV Panels 90X This permit is for the energization of the MPZs, Ametec, solar panels and associated equipment. [SEP-01-17 Doug Burkhardt] Please bring as-built drawings to Engineering. The isolations do not match the design drawings or the current panel schedules. How is the PV side being LOTO'd?

[SEP-01-17 Douglas Brunkow] PV side is the disconnects on the Inverters.  These disconnects are the DC side of the system.
LP-2931 08-28-2017 11:58 AM 08-03-2017 Huebschle, Mark Crouse Construction 77A HVAC upgrade 77A Relocate a gas valve for new AHU installation  
LP-2930 08-23-2017 03:27 PM 08-07-2017 Brunkow, Douglas Crouse Construction B50B room 1232 Remodel 50B Contractor will be adding additional outlets and removing partitions from the space.  
LP-2929 08-23-2017 03:24 PM 08-28-2017 Brunkow, Douglas Crouse Construction Room 1232 Remodel 50B Contractor will be changing out the existing lights in the room to LED lights  
LP-2928 08-23-2017 01:26 PM 08-24-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Panelboard 218A4A will be locked out at the main until future work is required downstream at three new pumps and one new cooling tower.  No work will occur in 218A4A once this LOTO is established. [AUG-30-17 Katherine Johnson] Approval was obtained by Murphy for final release to RI via phone call .
LP-2927 08-23-2017 12:53 PM 08-24-2017 Bolles, Benjamin W.E. Lyons B2 Temporary Chiller 34 Install new breaker in switchgear 309A at 309A-6.  Install conductors from 309A-6 to cam lock box on exterior of building 34.  
LP-2926 08-23-2017 12:49 PM 08-24-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Install new 100 amp fuses in ADF-2-37 / ADF-3-37.  install new trip unit on 218A main.  Install new trip units on 218A-1 and 218A-2.  Install new circuit breakers 218A-3 and 218A-4.  Install new conductors from 218A-3 and 218A-4 to new panelboards 218A3A and 218A4A.  
LP-2925 08-23-2017 12:31 PM 09-15-2017 farrell, randy PDE Heat exchanger and pumps 59 Install 2 circuits for CW and TW pump heaters.  
LP-2924 08-21-2017 01:58 PM 08-24-2017 Huebschle, Mark CAL NEVA 90 Heat Pump Replacement 90 Disconnect AC-28, pull wiresto allow relocation of conduit, reconnect.  
LP-2923 08-21-2017 10:12 AM 08-23-2017 Bolles, Benjamin W.E. Lyons B2 Temporary Chiller 34 Open circuit breaker 309A6 to support the temporary chiller for the B37 ALS cooling tower project.  Connect cam lock cables to cam lock box from new temporary chiller.  Energize new temporary chiller. [AUG-21-17 Doug Burkhardt] It states you want to LOTO Bank 309 with Circuit 309A-5. This is not possible. Please revisit.

[AUG-22-17 Benjamin Bolles] Corrections completed Ben Bolles.

[AUG-22-17 Katherine Johnson] Where will you be performing zero energy verification? 
LP-2921 08-19-2017 01:45 PM 08-19-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) SW-A6 Bus 2 maintenance 64C Battery charger maintenance  
LP-2920 08-19-2017 01:41 PM 08-19-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) SW-A6 Bus 2 maintenance 64C Maintenance on battery chargers in SW-A6 line 2  
LP-2919 08-17-2017 01:39 PM 08-21-2017 Jew, Ernie LBNL LOTO Procedure Dent meter install in panel E594A 59 Install Dent meter, CTs, and associated wiring in panel E594A for the PUE cauculation [AUG-18-17 Doug Burkhardt] Work with Jim Murphy on this. I believe you need to LOTO the start battery as well. This sounds like you are just removing the Call to Start controls, but the genset  can still be started manually.
LP-2918 08-17-2017 07:42 AM 09-05-2017 Samatua, Tipasa Total Environmental & Power Systems, Inc: (TEPS) ESIP Pnl Brd Rpl 77 Subcontractor to replace existing electrical panel boards at building 77 as part of the ESIP Corrective Action program  
LP-2917 08-17-2017 07:26 AM 09-06-2017 Samatua, Tipasa Total Environmental & Power Systems, Inc: (TEPS) ESIP B. 77 Pnl Brd Rpl 77 Subcontractor to replace electrical panel boards 72A1A, 72A1B, 78A, 78B, 78C & 78D as part of the ESIP Corrective Action.  
LP-2916 08-16-2017 09:10 AM 08-24-2017 Samatua, Tipasa Crouse Construction B. 83 Renovation 83 Subcontractor to demo various abandoned conductors and ad new outlets. (Rearranging of panel)  
LP-2915 08-15-2017 09:13 AM 08-18-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) SW-A6 Line 2 Maintenance 064C Emerson to perform Electrical PM on:
A.  SW-A6 Bus 2 (12KV Breakers, CPT's, PT's, Metering Equipment)
B.   ADF-1-88, ADF-2-88, ADF-3-88, ADF-4-88, Bank 80, Bank 198
C.  GS-1-50A, ADF-1-50A, ADF-1-50B, ADF-2-50B, GS-1-50B, Bank 
     480, Bank 38, Bank 35
D.  GS-3-70, GS-4-70, ADF-1-50, ADF-1-70, ADF-3-70, ADF-2-
     70A, Bank 25, Bank, 30, Bank 70, Bank 31

Pinnacle will be doing the following work under the same LOTO to Cut and isolate conductors at GS-1-50B back into the manhole and splice in T-Bodies and reconnect all cables bypassing the gas switch in preparation of the Gas Switch Replacement
 
LP-2914 08-14-2017 02:09 PM 08-21-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Install, test and commission new chiller controls [SEP-15-17 Katherine Johnson] Un-approved to allow for modifications.
LP-2913 08-14-2017 01:46 PM 08-16-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) SW-A6 Line 2 Maintenance 064C This LOTO permit is to begin the Isolations and Grounds for the outage on 8-19-17.  
LP-2912 08-14-2017 01:25 PM 08-21-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Install, test and commission new controls [AUG-17-17 Doug Burkhardt] Gas Valves isolation does not match panel schedules. 

[AUG-17-17 Doug Burkhardt] Disregard previous comments.
LP-2911 08-14-2017 12:36 PM 08-21-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Install, test and commission new AHU  
LP-2910 08-14-2017 12:31 PM 08-21-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Install, test and commission new AHU  
LP-2909 08-14-2017 12:24 PM 08-21-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Install, test and commission new pump  
LP-2908 08-14-2017 12:21 PM 08-21-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Install, test and commission new pump  
LP-2907 08-14-2017 12:17 PM 08-21-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Install, test and commission new AHU  
LP-2906 08-14-2017 12:06 PM 08-21-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Install, test and commission new chiller  
LP-2905 08-14-2017 11:39 AM 08-21-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Demo existing circuits to breakers, install new breaker, install new conduits, pull new wire, torque and megger [AUG-17-17 Doug Burkhardt] Note. I changed the isolation point from "D" to "5" and marked up the SLDs to match.

[AUG-17-17 Doug Burkhardt] Disregard Previous Comments.

[AUG-28-17 Katherine Johnson] Will you be using a remote racking mechanism?  Where will zero energy verification be performed?

[AUG-28-17 Mark Huebschle] Remote racking, zero voltage verified at panel 72D   7.7cal/cm^2
LP-2904 08-14-2017 11:38 AM 08-15-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Isolate 12" treated water supply header on 1st floor to install temperature sensor. [AUG-17-17 Doug Burkhardt] Approved per MCD.
LP-2903 08-11-2017 03:14 PM 08-18-2017 Colton, Floyd Stations Move Furniture Cubicles B90 Remove furniture cubicles 1106a, 1106b, 1106c and 1106d so that the floor of RM1106 can be leveled. When leveling work is complete the furniture will be reinstalled.

[AUG-15-17 James Murphy] Bank 539 is a 45kVA transformer therefore no arc flash hazard.
LP-2902 08-11-2017 02:03 PM 08-18-2017 Huebschle, Mark CAL NEVA Bldg. 90 HVAC upgrade 90 Demo AC-24-90 and AC-25-90  
LP-2901 08-11-2017 08:39 AM 08-17-2017 magstadt, michael Infrequent Subcontractor Power Bank 1B Battery Switch out 50B Change out the hot swappable batteries. 

No access to the back of the unit will be authorized unless a ZVV has been performed by a QEW 2.
 
LP-2900 08-11-2017 08:32 AM 08-17-2017 magstadt, michael Infrequent Subcontractor Power Bank 1A Battery Switchout 50B Change out the hot swappable batteries. 

No access to the back of the unit will be authorized unless a ZVV has been performed by a QEW 2.
 
LP-2899 08-10-2017 11:31 AM 08-25-2017 Samatua, Tipasa Total Environmental & Power Systems, Inc: (TEPS) ESIP Sitewide 77 Subcontractor to replace existing Electrical Panel Boards as part of the ESIP sitewide corrective action  
LP-2898 08-10-2017 06:54 AM 08-31-2017 farrell, randy PDE EPO phase 2 59 Install new controller preform start up.  
LP-2897 08-09-2017 11:46 AM 08-10-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Install new 14" pipe riser through existing sump basin between two supply valves. [AUG-10-17 Doug Burkhardt] Approved per MCD.
LP-2896 08-09-2017 07:07 AM 08-24-2017 farrell, randy XL Construction Heat exchanger and pumps 59 Loto valves to isolate water to small part of 30" manifold [AUG-11-17 Doug Burkhardt] Approved per MCD.

[AUG-24-17 Katherine Johnson] Need contractor info.

[SEP-06-17 Katherine Johnson] Done

[SEP-11-17 James Murphy] Electrical Isolations added after Approval
LP-2895 08-08-2017 07:02 AM 08-21-2017 Samatua, Tipasa Total Environmental & Power Systems, Inc: (TEPS) ESIP Sitewide 77 Subcontractor to replace various (5)  electrical panel boards at building 77 Sheet Metal Shop as part of the Electrical Safety Improvement Project (ESIP) across the laboratory.  
LP-2894 08-08-2017 06:01 AM 08-11-2017 Samatua, Tipasa Crouse Construction B. 83 Renovation 83 Subcontractor (PDE) to change out  an existing breaker to accommodate the new dishwasher.  
LP-2893 08-04-2017 01:48 PM 08-31-2017 farrell, randy XL Construction Hxp 59 LOTO panel 596A1A8A to install new breaker, bus kit, feeeders and conduit. Do torques, meg and inspection. [AUG-24-17 Katherine Johnson] Need contractor info.

[SEP-06-17 Katherine Johnson] Done
LP-2892 08-04-2017 01:43 PM 08-31-2017 farrell, randy XL Construction Hxp 59 Loto panel 596A1A5A and istall breaker, bus kit, feeders and conduit into panel. torque, meg and inspect. [AUG-24-17 Katherine Johnson] Need contractor info.

[SEP-06-17 Katherine Johnson] Done
LP-2891 08-04-2017 01:31 PM 08-11-2017 Huebschle, Mark Crouse Construction 77A HVAC upgrade 77A Demo of existing AHU's  
LP-2890 08-04-2017 11:16 AM 08-07-2017 Espinoza, Jacob Infrequent Subcontractor Machine start up 77 Perform connections of components within the machine during the startup process followed by a NRTL inspection.   
LP-2888 07-31-2017 01:09 PM 08-04-2017 Bolles, Benjamin W.E. Lyons B37 Controls Upgrade 37 Install new 20amp 120v circuit breaker for control panel e-power.  See LP 2516 for reference. [JUL-31-17 Benjamin Bolles] 
LP-2887 07-31-2017 01:03 PM 08-04-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Isolate 12" treated water return header on 1st floor to install flow meter. [AUG-04-17 Doug Burkhardt] Approved per MCD
LP-2886 07-31-2017 12:54 PM 08-09-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Remove and relocate 20" main water supply header in street over to roof top of B37.  Isolate 20" main supply water under cooling tower; isolate three 14" manifold valves on 2nd floor. [AUG-04-17 Doug Burkhardt] Approved per MCD
LP-2885 07-26-2017 03:58 PM 08-01-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Demo AHU-003-77A  
LP-2884 07-26-2017 03:52 PM 08-01-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Demo AHU-002-77A  
LP-2883 07-26-2017 03:37 PM 08-01-2017 Huebschle, Mark Crouse Construction 77A HVAC Upgrade 77A Demo AHU-001  
LP-2882 07-24-2017 02:58 PM 08-01-2017 Huebschle, Mark CAL NEVA Bldg. 90 HVAC upgrade 90 Replace breakers 3 & 4 in Panel 90A9A  
LP-2881 07-21-2017 06:20 AM 08-04-2017 Samatua, Tipasa Crouse Construction B. 83 Renovation 83 Subcontractor to remove existing Dark Room Light fixtures in room 412 and replace with LED fixtures for the new IT closet. [JUL-31-17 Doug Burkhardt] Arc Flash data is missing.

[JUL-31-17 Tipasa Samatua] Please see photo of ARC flash label attached

[JUL-31-17 Katherine Johnson] Updated to reflect AC and not DC per communication with T.
LP-2880 07-21-2017 06:11 AM 08-09-2017 Samatua, Tipasa Crouse Construction B. 83 Renovation 83 Subcontractor to add circuit breakers and remove abandoned conductors. [AUG-08-17 Doug Burkhardt] Note that panel schedule shows the circuits are out of order.
LP-2879 07-21-2017 06:05 AM 08-03-2017 Samatua, Tipasa Crouse Construction B. 83 Renovation 83 Subcontractor to add new circuit and remove conductors.  
LP-2878 07-16-2017 05:39 PM 07-17-2017 Stanley, Gregory Matrix HG, Inc B400 Chiller Repairs 400 Swapped spare compressor located in circuit #2 for failed compressor in circuit #1.   
LP-2876 07-07-2017 12:26 PM 07-12-2017 Brunkow, Douglas PDE Flexlab PV Panels 90X Contractor will be energizing the AC line service to the MPZs that will be feeding the inverters.   
LP-2875 07-07-2017 10:47 AM 07-11-2017 Stanley, Gregory PDE 307 Lighting Repair 210 Replace failed lighting ballast in Room 307  
LP-2874 07-07-2017 10:40 AM 07-11-2017 Stanley, Gregory PDE Lab 140 Lighting Repair July17 100 Replace ballast in lighting fixture  
LP-2873 07-07-2017 10:30 AM 07-11-2017 Stanley, Gregory PDE 119 Northen Circuit Mod 100 Reconfigure L3 circuits 23/25 and 39/41.  
LP-2872 07-07-2017 08:05 AM 07-10-2017 Jew, Ernie Eaton Electrical UPS Services UPS 2 battery preventive maintenance 59 Perform preventive maintenance on UPS2 batteries in Cabinet #3  
LP-2871 07-07-2017 08:01 AM 07-10-2017 Jew, Ernie Eaton Electrical UPS Services UPS 2 battery preventive maintenance 59 Perform preventive maintenance on UPS2 batteries in Cabinet #2  
LP-2870 07-07-2017 07:56 AM 07-10-2017 Jew, Ernie Eaton Electrical UPS Services UPS 2 battery preventive maintenance 59 Perform preventive maintenance on UPS2 batteries in Cabinet #1  
LP-2869 07-07-2017 07:47 AM 07-10-2017 Jew, Ernie Eaton Electrical UPS Services UPS 1 battery preventive maintenance 59 Perform preventive maintenance on UPS1 batteries in Cabinet # 3  
LP-2868 07-07-2017 07:34 AM 07-10-2017 Jew, Ernie Eaton Electrical UPS Services UPS 1 battery Preventive Maintenance 59 Perform preventive maintenance on UPS1 batteries in Cabinet # 2.  
LP-2867 07-06-2017 02:18 PM 07-10-2017 Jew, Ernie Eaton Electrical UPS Services UPS1 battery preventive maintenance 59 Perform preventative maintenance on UPS1 batteries in Cabinet #1  
LP-2866 07-05-2017 10:14 AM 07-07-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Relocate 14" tower water supply valve TWS 3-203 for new manifold riser piping. [JUL-06-17 Doug Burkhardt] Approved per MCD
LP-2865 07-05-2017 09:58 AM 07-12-2017 Homon, Kevin Infrequent Subcontractor Cubical reconfiguration at 76-0222 076 76-222 (WPC) area will be reconfigured. Will need Electricians to de-energize and re-energized the cube panels.  
LP-2864 06-30-2017 02:31 PM 07-07-2017 Brunkow, Douglas PDE Flexlab Photovoltaic install 90X Installing a new 110 volt outlet on the new rack installed by Solar City.  
LP-2863 06-29-2017 12:32 PM 07-05-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Install new 14" pipe riser through existing sump basin between two supply valves. [JUN-29-17 Doug Burkhardt] Approved per MCD
LP-2862 06-29-2017 12:26 PM 07-05-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Install new 14" pipe riser through existing sump basin between two supply valves. [JUN-29-17 Doug Burkhardt] Approved per MCD
LP-2861 06-28-2017 12:43 PM 06-29-2017 Standridge, Dan Infrequent Subcontractor Sprinkler System Modificaiton 77 Adding a fire protection sprinkler to room 077-142c.  The crane will need to be locked out to avoid movement to workers in addition to the fire sprinkler system.  
LP-2860 06-28-2017 09:48 AM 07-05-2017 Cota, David Infrequent Subcontractor Repair motorized fire door 84 Reset door and replace motor if required  
LP-2859 06-23-2017 02:47 PM 06-30-2017 Huebschle, Mark Crouse Construction Bldg 62 glove box anchoring 62 Glove box in room 150 to be anchored, conduits from panel 67A13C to be LOTO'd prior to drilling the floor.  
LP-2858 06-21-2017 09:10 AM 06-24-2017 Brunkow, Douglas PDE Flexlab PV Panels 90 New electrical meter will need data added to it after it is installed and lotoed.  
LP-2857 06-21-2017 08:52 AM 06-23-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Remove sand filter, motor and pump.  All scheduled for demolition.  
LP-2856 06-20-2017 02:58 PM 06-20-2017 Kemper, Timothy Infrequent Subcontractor IGB Main Water Line 91 Remove blind flange and add new piping and pancake blind flange. [JUN-21-17 Doug Burkhardt] Per Mike Dong: "Please...put the water valve number on the [permit]."

[JUN-21-17 Ian White] Valve number added under isolation point on non electrical isolation spreadsheet

[JUN-23-17 Doug Burkhardt] Approved per MCD
LP-2855 06-20-2017 11:05 AM 06-27-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Turn off VFD, close supply and return valves before and after check valve to replace check valve on 8" piping. [JUN-21-17 Doug Burkhardt] Non-electrical approved by MCD.
LP-2854 06-20-2017 10:45 AM 06-23-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Turn off VFD, close supply and return valves before and after check valve to replace check valve on 8" piping. [JUN-21-17 Doug Burkhardt] Non-electrical approved by MCD.
LP-2853 06-16-2017 04:25 PM 06-19-2017 Huebschle, Mark Infrequent Subcontractor S-Road Water Main 32 Replace 200' section of water main [JUN-20-17 Doug Burkhardt] Approved per MCD
LP-2852 06-15-2017 12:25 PM 06-15-2017 rcvelasco@lbl.gov LBNL LOTO Procedure Investigate Power Outage to 50 Area 70 Investigate cause of power outage to buildings 50  
LP-2851 06-14-2017 01:53 PM 06-14-2017 rcvelasco@lbl.gov LBNL LOTO Procedure Investigate Power Outage to 50/70 Area 64C Investigate cause of power outage to buildings 50, 54, 70, 70A [JUN-14-17 James Murphy] Switch Tag Reviewed by Murphy, not able to up load at this time
LP-2849 06-12-2017 02:30 PM 06-16-2017 rcvelasco@lbl.gov Eaton (Cutler-Hammer) Bldg 15 bus duct repair 15 Inspect bus duct  
LP-2848 06-12-2017 12:14 PM 06-15-2017 Brunkow, Douglas PDE Flexlab PV Panels 90X Contractor will be installing a new 150 amp breaker in panel 659A16A under loto LP-2843.  This loto will lockout the newly installed breaker until the EVAP is approved and the startup can begin.  Will also be used if there are issues found during the startup so that the circuit can be shutdown to correct them. [JUN-28-17 Mark Scott] Arc flash label updated on 6/19/17. Updated LOTO Permit to match. Now <1.2 cal/cm2. MAS 6/28/17
LP-2847 06-12-2017 06:31 AM 06-12-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Demolish hot water riser pipes from t-section on exterior of building valve TW-3-204.  Demolish hot water riser pipes from cross-section on exterior of building valve TW-3-206.  New blind flanges will be placed over valves where riser pipes are removed. [JUN-12-17 Doug Burkhardt] Approved by MCD
LP-2846 06-07-2017 10:49 AM 06-09-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 34 Lock out new breakers for installation of three VFD's 37-VFD-020, 37-VFD-021 and 37-VFD-022 for three motors/pumps 37-GP--144, 37-GP-145 and 37-GP-146 [JUN-08-17 Doug Burkhardt] On hold per BB

[JUN-08-17 Benjamin Bolles] Corrections completed.  BGB
LP-2845 06-06-2017 09:03 AM 06-06-2017 Bolles, Benjamin W.E. Lyons B37 ALS cooling tower replacement 37 Demolition of existing cooling tower fans CT 100 and CT 101.

Demolition of chain hoist circuit, cable and conduit.
 
LP-2844 06-05-2017 11:19 AM 06-15-2017 Brunkow, Douglas PDE Flexlab PV Panels 90X Contractor will be replacing breaker feeding 659A16A and adding CTs for a metering system. [JUN-06-17 Doug Burkhardt] Added circuit info to isolation point.
LP-2843 06-02-2017 03:05 PM 06-14-2017 Brunkow, Douglas PDE Flexlab PV install 90X2 Contractor will be replacing breakers and adding new breakers and associated conduit and wires into panel 659A16A to support the installation of solar panels.  
LP-2842 05-30-2017 12:23 PM 06-01-2017 Bolles, Benjamin W.E. Lyons B37 ALS cooling tower replacement 37 Demolition of existing cooling tower fans and motor heaters CT 100 and CT 101.

Demolition of site lighting, cable and conduit and two outdoor receptacles and chain hoist circuits.
 
LP-2841 05-22-2017 11:41 AM 05-22-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 LOTO supply valves at sump 100 and sump 101 for cut-over of new 14" pvc supply header. [MAY-22-17 Doug Burkhardt] Approved by MCD
LP-2840 05-19-2017 09:40 AM 05-19-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Connect LLC circuit, liquid level controller, to existing thermistor circuit in junction box fed from E231A-15.  
LP-2839 05-18-2017 12:41 PM 05-22-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Isolate motor heater circuits for GP-100-37, GP-101-37 and GP-102-37.  These are currently isolated in a junction box waiting for new pumps. [MAY-18-17 Doug Burkhardt] electrical approved by dAb
non-electrical approved by MCD
LP-2838 05-18-2017 12:36 PM 05-22-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Isolate circuits in a junction box waiting for installation of new motors.  
LP-2837 05-18-2017 08:00 AM 05-22-2017 Stanley, Gregory PDE 407/408 Lighting Mods 400 Modify lighting supply power and install motion sensor that covers JGI Director's office desk.   
LP-2836 05-15-2017 03:33 PM 05-22-2017 Huebschle, Mark PDE 64-147 Two new circuits 64 Panel 129A4A

Use two spare single phase circuits at 25 slot and install new 30A breaker. Furnish and install new conduit to Room 147 and associated new receptacle.
[MAY-18-17 Doug Burkhardt] Please label equipment with the labels Jeffri provided.
LP-2835 05-15-2017 03:29 PM 05-22-2017 Huebschle, Mark PDE 64-147 Two new circuits 64 Replace ckt 30 breaker with a  50 amp breaker in Panel 512A7AD1A4A . Install a new disconnect and receptacle in room 147, associated conduit and conductors.  
LP-2834 05-12-2017 08:30 AM 05-15-2017 rcvelasco@lbl.gov Emerson Reliability Services (Vertiv) Grizzly Line 2 Transformer Test and Repair 036 We will isolate the bank 2 transformer so that Emerson could:
1. Test the line 2 Transformer ( hi-pot)
2. Megger wires from load side of transformer into SW-A1 (Brkr 102)
3. Line 2 Neutral resistor
 
LP-2833 05-11-2017 01:06 PM 05-12-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 34 Adding and removing temporary power to panel 309A3A as needed to support the 37 Cooling Tower Replacement Project.  
LP-2832 05-11-2017 01:01 PM 05-12-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 34 Perform work associated with the energization of the new filtration motor 37-FL-101 per section 3 of the PUROFLUX Start-up Procedure.  
LP-2831 05-11-2017 10:09 AM 05-16-2017 Jew, Ernie Eaton Electrical UPS Services UPS 1 Fan Repair 59 Troubleshoot and Repair Fan Alarm on UPS1  
LP-2830 05-10-2017 09:47 AM 05-10-2017 rcvelasco@lbl.gov LBNL LOTO Procedure Repair TSW-1-62 62 TSW-2-62 will not transfer back to Normal. Halmuth Aukes to troubleshoot and repair.  
LP-2829 05-10-2017 08:26 AM 05-12-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 34 Lock out new breakers for future installation of three VFD's 37-VFD-020, 37-VFD-021 and 37-VFD-022 for three motors/pumps 37-GP--144, 37-GP-145 and 37-GP-146 and Cooling Tower Fan motor 37-CT-103 [MAY-11-17 Doug Burkhardt] Can you coordinate the work with Engineering? The panel schedules do not match this LOTO. Is this all new work?
LP-2828 05-10-2017 06:28 AM 05-12-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Remove GP-100-37, GP-101-37 and GP-102-37.  
LP-2827 05-09-2017 12:14 PM 05-10-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Install new 14" piping that ties into 20" cooling supply header at Cooling Tower Sump 101.  Tie in will not be made to 20" sump at this time and will occur under LP 2817.  New piping will be run from 14" valve TTV 3-37 which will be locked closed under this permit.  
LP-2826 05-08-2017 11:40 AM 05-09-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Connect new CT 103 liquid level controller to existing circuit at junction box of CT 102.

Connect CT 103 thermistor to exisiting circuit at junction box of CT 102.
 
LP-2825 05-05-2017 01:58 PM 05-05-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Remove and replace impeller in GP-102-37. [MAY-05-17 Doug Burkhardt] Non-electrical approved by MCD
LP-2824 05-03-2017 11:00 AM 05-05-2017 Stanley, Gregory PDE Room 122 NextSeq Circuit Mods 100 Work in the raceway down stream from EL5D to install new receptacles and pull wire.  No work will be performed in EL5D.  That work is performed under a separate permit.  
LP-2823 05-03-2017 10:56 AM 05-05-2017 Stanley, Gregory PDE NextSeq Circuit Mods 100 Install new two pole breakers for circuits 17/19 and 35/37.  Wiring accordingly.   
LP-2821 05-02-2017 08:08 AM 05-04-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Remove and replace wafer valve TW 02-37 below sump in room 203.  
LP-2820 05-02-2017 07:47 AM 05-04-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Remove and replace wafer valve TW 01-37 below sump in room 203.  
LP-2819 05-01-2017 01:24 PM 05-04-2017 Brunkow, Douglas Goebel Paving/Grading Old Town 7 Contractor will be flushing a water line that was repaired.  
LP-2818 05-01-2017 08:23 AM 05-01-2017 Cota, David Infrequent Subcontractor B-77 UMF 77 Perform work near the proximity of the crane.  No work will be performed within 42" of the crane rail.  This will be mechanical only. [MAY-01-17 David Cota] I changed the breaker to match the photo i sent in my text.
LP-2817 04-28-2017 12:51 PM 05-02-2017 Bolles, Benjamin W.E. Lyons B37 ALS Cooling Tower Replacement 37 Close cooling tower supply valves that supply water to cooling tower 101 sump to tie in new 14" piping. [MAY-01-17 Doug Burkhardt] Per MCD.
LP-2816 04-28-2017 07:07 AM 05-16-2017 Stanley, Gregory Steris Corp PM on B-100 Autoclave Steam Generator 100 Annual Preventative Maintenance Check. Includes blowing down the steam generator; removing and cleaning the conductivity probes; inspecting contactors and measuring insulation resistance.  
LP-2815 04-25-2017 02:17 PM 04-27-2017 Marietta, Peter Infrequent Subcontractor Bldg. 86 Autoclave 86 Replace the pump for the Autoclave under the direct field supervision by a lab authorized QEW.    
Result Pages:  1  2  3  4  5  6    
Report Name *
Description
Field label
Column heading override
Justification
What does auto mean?
Fields in:

Fields to Extract:

Name for the new table:
Items in the new table are called:

When you bring additional fields into a conversion, Quick Base often finds inconsistencies. For example, say you're converting your Companies column into its own table. One company, Acme Corporation, has offices in New York, Dallas and Portland. So, when you add the City column to the conversion, Quick Base finds three different locations for Acme. A single value in the column you're converting can only match one value in any additional field. Quick Base needs you to clean up the extra cities before it can create your new table. To do so, you have one of two choices:

  • If you want to create three separate Acme records (Acme-New York, Acme-Dallas and Acme-Portland) click the Conform link at the top of the column.
  • If the dissimilar entries are mistakes (say Acme only has one office in New York and the other locations are data-entry errors) go back into your table and correct the inconsistencies—in this case, changing all locations to New York. Then try the conversion again.

Read more about converting a column into a table.

Show fields from Show fields from Show fields from a related table

We're glad you're interested in doing more with Quick Base!

Now we need to make you official before you share apps or manage your account.

Verifying your email lets you share Quick Base with others in your company.

Your work email
Your company